  "docId": "019de518-dbe5-74df-9dbb-3e66f5eed4bb",
  "docSlug": "917d6d7ccf5c26956f3fdb3cb61ab659",
  "documentTitle": "Antofagasta | Results Presentation Deck | 35 slides",
  "authorId": "antofagasta",
  "authorName": "Antofagasta",
  "documentKindSlug": "conference-presentation",
  "documentKindLabel": "Conference presentation",
  "sourceTypeSlug": "investor_relations",
  "sourceTypeLabel": "Investor relations",
  "presentationDate": "2025-02-01 00:00:00",
  "orientation": "landscape",
  "aspectRatio": 1.7777778,
  "pageNumber": 23,
  "pageCount": 35,
  "prevPage": 22,
  "nextPage": 24,
  "slideType": "propose_solution",
  "function": "propose_solution",
  "density": "overcrowded",
  "nDataPoints": 4,
  "notes": null,
  "elementsJson": null,
  "metadataConfidence": 0.9,
  "imagePath": null,
  "slideHref": "/slides/019de518-dbe5-74df-9dbb-3e66f5eed4bb/23",
  "deckHref": "/decks/019de518-dbe5-74df-9dbb-3e66f5eed4bb",
  "deckJsonHref": "/decks/019de518-dbe5-74df-9dbb-3e66f5eed4bb.json",
  "deckAnchorHref": "/decks/019de518-dbe5-74df-9dbb-3e66f5eed4bb#slide-23",
  "components": [
    {
      "bbox": {
        "h": 0.337,
        "w": 0.443,
        "x": 0.043,
        "y": 0.223
      },
      "kind": "image",
      "text": "Image: Access road construction, ahead of installing pipeline (lower section)",
      "attrs": null,
      "subkind": "photo",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "34e7ece3-8470-4d53-badc-7337bb2f1c19",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.337,
        "w": 0.443,
        "x": 0.53,
        "y": 0.223
      },
      "kind": "image",
      "text": "Image: Water tanks for existing desalination plant (right) and expansion (left)",
      "attrs": null,
      "subkind": "photo",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "4fa91193-4e0f-470c-bd0e-8c999e9527d0",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.239,
        "w": 0.443,
        "x": 0.53,
        "y": 0.59
      },
      "kind": "list",
      "text": "Desalination plant expansion\nDescription: Project to double capacity of existing desalination plant to 800 l/s.\nConstruction timeline: 2024-2027.\nCurrent activities: Following a successful mobilisation of personnel and equipment, construction work is expected to commence in Q1 2025.",
      "attrs": null,
      "subkind": "bullet",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "15c057f2-8eec-4c06-8a52-8477aacf80be",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.316,
        "w": 0.443,
        "x": 0.043,
        "y": 0.59
      },
      "kind": "list",
      "text": "Concentrate pipeline and El Mauro Enclosures\nDescription: Installation of a new 125km concentrate pipeline and development of certain planned enclosures at the El Mauro tailings storage facility.\nConstruction timeline: 2024-2027.\nCurrent activities: Work focused on trench excavation work and the welding of pipe sections. Additional activities include the construction of access roads and preparatory tunnel works in elevated section of route. As of December 2024, more than 2,500 contractors mobilised at Los Pelambres' current projects.1",
      "attrs": null,
      "subkind": "bullet",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "6e3dcde2-284c-460b-a2bb-bfe95273c57f",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.02,
        "w": 0.596,
        "x": 0.083,
        "y": 0.94
      },
      "kind": "source-note",
      "text": "1. Combined figure for both the projects shown here (being (1) concentrate pipeline and El Mauro enclosures, and (2) desalination plant expansion)",
      "attrs": null,
      "subkind": null,
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "b01a7ea7-3eef-49ca-8660-0a56768f53af",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.086,
        "w": 0.469,
        "x": 0.043,
        "y": 0.066
      },
      "kind": "title",
      "text": "Projects update: Los Pelambres Creating a platform for future growth",
      "attrs": null,
      "subkind": "headline",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "04e0044b-5767-427b-9d6a-cb93ab229efe",
      "frameworkName": null,
      "frameworkSlug": null
    }
  ],
  "metrics": [],
  "tools": [],
  "frameworks": [],
  "arcBeats": [],
  "loops": [],
  "imagePathAlt": null,
  "thumbSrc": null,
  "thumbSrcAlt": null,
  "locked": true
}