  "docId": "019de517-5e5f-753b-adad-2cd934aab037",
  "docSlug": "ff43e93085f05174f4f52c2d4d80838f",
  "documentTitle": "Li-Cycle | Results Presentation Deck | 24 slides",
  "authorId": "li-cycle",
  "authorName": "Li-Cycle",
  "documentKindSlug": "conference-presentation",
  "documentKindLabel": "Conference presentation",
  "sourceTypeSlug": "investor_relations",
  "sourceTypeLabel": "Investor relations",
  "presentationDate": "2023-11-01 00:00:00",
  "orientation": "landscape",
  "aspectRatio": 1.7777778,
  "pageNumber": 6,
  "pageCount": 24,
  "prevPage": 5,
  "nextPage": 7,
  "slideType": "other",
  "function": "frame_situation",
  "density": "balanced",
  "nDataPoints": 0,
  "notes": null,
  "elementsJson": null,
  "metadataConfidence": 1,
  "imagePath": null,
  "slideHref": "/slides/019de517-5e5f-753b-adad-2cd934aab037/6",
  "deckHref": "/decks/019de517-5e5f-753b-adad-2cd934aab037",
  "deckJsonHref": "/decks/019de517-5e5f-753b-adad-2cd934aab037.json",
  "deckAnchorHref": "/decks/019de517-5e5f-753b-adad-2cd934aab037#slide-6",
  "components": [
    {
      "bbox": {
        "h": 0.02,
        "w": 0.079,
        "x": 0.86,
        "y": 0.94
      },
      "kind": "image",
      "text": "Li-Cycle",
      "attrs": {},
      "subkind": "logo",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "c883b270-5b0d-4f73-bd5f-979afe255c21",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.44,
        "w": 0.859,
        "x": 0.069,
        "y": 0.45
      },
      "kind": "list",
      "text": "Cash Preservation, Spoke and Financing Update\nLiquidity Management\nFocus on liquidity management with actions already taken:\nSG&A optimization\nSpoke operations\nGrowth capital project optimization\nCorporate Financing\nStrategic financing opportunities\nProject Financing\nU.S. Department of Energy (DOE) Loan Programs Office (LPO)",
      "attrs": {},
      "subkind": "bullet",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "176720b6-bc94-454f-911c-aa06c8ec725c",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.179,
        "w": 0.859,
        "x": 0.069,
        "y": 0.276
      },
      "kind": "list",
      "text": "Rochester Hub Review\nPhasing Approach\nOpportunities to phase key end-product production (Existing Approach and Phased Approach)\nConstruction Strategy\nOpportunities to optimize construction and contracting strategy",
      "attrs": {},
      "subkind": "bullet",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "832c7e34-563e-4828-a5c2-bca69ceb5985",
      "frameworkName": null,
      "frameworkSlug": null
    },
    {
      "bbox": {
        "h": 0.03,
        "w": 0.939,
        "x": 0.029,
        "y": 0.06
      },
      "kind": "title",
      "text": "Key Considerations in Comprehensive Review of the Rochester Hub Project",
      "attrs": {},
      "subkind": "headline",
      "toolName": null,
      "toolSlug": null,
      "confidence": null,
      "componentId": "d25110fe-7c60-454a-834f-26da625b5f7c",
      "frameworkName": null,
      "frameworkSlug": null
    }
  ],
  "metrics": [],
  "tools": [],
  "frameworks": [],
  "arcBeats": [
    {
      "to": 6,
      "from": 4,
      "beatId": "f91075ea-43f3-4b6a-bdca-2d9189528402",
      "arcName": "Monroe's Motivated Sequence",
      "arcSlug": "monroes-sequence",
      "beatName": "Need",
      "beatSlug": "monroes-sequence-need",
      "evidence": "The problem statement and geographic map highlight the need for Li-Cycle's solution",
      "position": 1,
      "confidence": 0.8,
      "parentBeatName": "Complication",
      "parentBeatSlug": "complication"
    }
  ],
  "loops": [
    {
      "to": 9,
      "from": 4,
      "name": "Cost Of Inaction",
      "slug": "27-cost-of-inaction",
      "bestFor": "Urgent budget requests, compliance, risk mitigation",
      "matchId": "95df4152-2d91-4262-ac7f-28bdd5e20434",
      "evidence": "The presentation highlights the challenges and costs associated with the project pause",
      "position": 0,
      "objective": "What are the consequences of not pausing the Rochester Hub project?",
      "structure": "The Status Quo -> The Hidden Costs Accumulating -> The Future State of Inaction -> The Tipping Point",
      "confidence": 0.6,
      "description": "Quantify what happens if the audience does nothing"
    }
  ],
  "imagePathAlt": null,